In June of 2014, the MCEC completed construction of a Cultural Center in the heart of Pangling, Nepal, on land donated by the community. Inauguration ceremonies were held in August with community leaders, Geshe Sobnam and donors.
The Cultural Center will be a platform to preserve, share and pass on traditional farming methods; to sustain weaving, shoe-making and other art of clothes-making; to continue traditional painting and wood carving practices; to practice indigenous folk medicine; and to learn indigenous music, singing and folk dancing to celebrate local festivals, e.g. harvest and the new year. This Cultural Center would also serve as a local gathering place for contact between younger and older villagers in such a way that a wide range of cultural practices would be sustained and passed on from generation to generation.
Estimated cost: $ 45000 USD
Government of Nepal | |||||||
Ministry of Local Development | |||||||
Office of District Development Committee | |||||||
District Technical Office | |||||||
Jomsom, Mustang | |||||||
Abstract of Cost | |||||||
Project Name:Cultural Hall construction | |||||||
Location: Pangling,Kagbeni,Mustang | |||||||
S.N | Particular of Items | Quantities | Units | Rate | Per | Amount | Remarks |
1 | Site clearance work | 625.00 | m2 | 9.59 | 5993.75 | ||
2 | E/W excavation work | 43.88 | m3 | 663.27 | 29100.97 | ||
3 | 1:1.5:3 pcc for rcc | 7.88 | m3 | 18630.80 | 146717.55 | ||
4 | Reinforcement work | 974.53 | 105.27 | 102588.90 | |||
5 | S/M work in 1:6 c/s mortar | 186.45 | m3 | 7825.94 | 1459134.77 | ||
6 | Wood work frame for D/W | 0.43 | m3 | 39239.80 | 16804.44 | ||
7 | Wood work for Door shutter | 1.17 | m2 | 3834.62 | 4472.70 | ||
8 | Glazed window shutter | 9.68 | m2 | 3252.46 | 31473.40 | ||
9 | Wood work for main post | 8.91 | m3 | 26732.05 | 238262.76 | ||
10 | 300 gaige plastic sheet in roof | 368.64 | m2 | 50.00 | 18432.00 | ||
11 | Sakhar mud filling and compaction in roof | 49.69 | m3 | 3500.00 | 173901.00 | ||
12 | 90mm dia drain pipe | 20.00 | rm | 1100.00 | 22000.00 | ||
13 | 20mm plaster in inner side of room over skirting | 196.56 | m2 | 314.23 | 61765.05 | ||
14 | Flooring work | 0.00 | |||||
14.1 | Earth filling work and compaction | 182.18 | m3 | 102.25 | 18628.11 | ||
14.2 | 38mm thick plate floor with (.10*.75) size wooden beam skirting in wall | 64.44 | m2 | 1286.84 | 82923.97 | ||
15 | 1:3 c/s pointing in outer wall | 309.40 | m2 | 187.15 | 57904.21 | ||
16 | Double coat white washing | 196.56 | m2 | 104.82 | 20603.42 | ||
Sub total cost of project | 2490707.02 | ||||||
17 | Electrification work all complete as per site incharge | 5 % of sub total | 124535.35 | ||||
18 | construction of toilet bathroom and all necessary arrangement of watersupply | 8 % of sub total | 199256.562 | ||||
Total cost of project | 2814498.93 | ||||||
VAT @ 13% | 365884.86 | ||||||
Contengencies @ 5 % | 140724.947 | ||||||
Grand total cost of project | 3321108.74 | ||||||
In words:- Thirty three lakhs twenty one thousand one hundred eight ruppes and seventy four paisa only |
- Mustang Culture and Education Centre
- Successful completion of the Cultural Center in Pangling
- Successful Completion of the Irrigation system to stabilize farming practice
- Successful Completion of the Children's Education System Supportive of Cultural and Spiritual Traditions.